How do you set up  a task or sub task to be due N days after you complete previous task?  For example, I want to follow up with a nag email a week after I ask for a meeting if the person does not respond.
1 reply
Hey @Michel Friedman
, great question. To do this:
1. First, set up a parent task to hold the multiple sub-tasks
2. Create the first subtask (e.g. Send an Email)
3. Create the second subtask and add a due date (e.g. 5 days after) and set to Automate = true

This will have the second email fire automatically 5 days after the first email is sent, regardless of when they were added to the stage.